Call for demonstration for June 23 by AHT EZ Llanada platform

  • According to the platform, as a result of the work of the project, the town would be isolated between the highway and the train.
Artikulu hau CC BY-SA 3.0 lizentziari esker ekarri dugu.

29 May 2018 - 08:57

The AHTrik EZ Llanada platform has announced that a demonstration will be held on June 23 in Agurain. On Friday, representatives of the political parties of the General Assemblies of Álava were watching the damage that the High-Speed Railway project to connect Pamplona-Vitoria-Gasteiz would cause in the Llanada, which was received by the citizens raising their arguments against the project.

The project foresees a strong impact in this area. In fact, they would have to make a trench that would be 900 meters long, 100 meters wide and 22 meters deep. As a result, the town would be isolated between the highway and the train.

The platform has started the line of initiatives through the mountain march organized last Saturday to the cross of Mirutegi.

Conferences in Agurain

In addition, on June 15, the Sala Muralla de Agurain will host a conference starting at 19:00. The speakers will be Iñigo Leza, spokesperson for the platform, Lierni Altuna, mayor of Aramaio, and David Hoyos and Josu Larrinaga, teachers and experts of the UPV/EHU.

This news has been published by Alava Alea and we have brought it to LUZ thanks to the license CC-by-sa.


You are interested in the channel: Abiadura Handiko Trena
Gorka Ovejero, platform against AAV: "It is said that the work of the polls is being obstructed by sabotage, but no complaint has been made"
The platform against the High Speed Train reported on Monday that the polling campaign being carried out by the Government of Spain and Navarre is not interrupted. The popular movement of Izurdiagan and Otsobin managed to stop the polling processes that were not legal and that... [+]

2025-05-07 | ARGIA
The network Euskal Herria Viva will camp in Donemiliaga to "organize the defense of the land"
The camp will take place from the 16th to the 18th of May in the town of Uribarri Jauregi, Álava, "threatened" by the AVE and a renewable project. "We will demonstrate our ability to organize resistance in areas that want to expropriate and we will move from filling the streets to... [+]

There is a link between Euskal Ya and AHT in Navarre

Do not look for this connection from Ezkio or Altsasu, let alone crossing the Ebro River through Castejón. The connection, or rather the connections, between the Basque Y and the AVE of Navarre is already a reality. It is these links in the plural that should concern us and... [+]


AHTren atzerapena gaitzesteko gutuna bidali diote Europako Batzordeko Garraio Komisarioari Pradalesek eta Roussetek

EAE, Akitania Berria eta Nafarroak osatutako euroeskualdearen batzarra egin dute Iruñean martxoaren 25ean. AHT izan dute topaketaren ondoko agerraldiko aipagai nagusien artean eta Akitania Berriko ardatza Hego Euskal Herriko trenbidearekin lotzeko konpromiso politikoa... [+]


AHTaren zundaketen aurkako ia bi urteko borrokaren balantzea

Datorren udaberrian, Stop AHT Zundaketak ekimenak bi urte beteko ditu. 2023ko maiatzean, ADIFek Itza, Sakana eta Goierriko udalei jakinarazi zien zundaketa geoteknikoak eta beste jarduketa batzuk egingo zituela AHTaren Nafarroako korridorea Euskal Y-arekin lotzeko alternatibak... [+]


Espainiako Sustapen Ministerioa: “Ez dakigu Ezkioko lotunea oso bideragarria den”

Josu Estarrona EH Bilduko Arabako senatariak egindako galderari erantzun dio Espainiako Sustapen Ministerioak, eta hor berretsi du Ezkioko aukera zailtasunez beteta dagoela.


PSNk AHTaren Gasteizko lotunearen alde egin du, Ezkiokoa ez dela “bideragarria” argudiatuta

"Gasteiztik egin ezean, ez da egingo", adierazi du PSNren bozeramaile Ramón Alzorrizek. Kontra azaldu dira Geroa Bai, UPN eta PP.


2025-02-20 | Gedar
Work to start the construction of the AVE between Vitoria and Burgos, moving forward
The first works to connect AVE with AHT Madrid and the AVE train will cost 2 billion euros. A demonstration was held this weekend in Pamplona to denounce the conditions of slavery in the construction works of the AVE.

AAV in the Southern Basque Country: An investment of 15 billion euros to reach Irun at high speed?
A demonstration against the high-speed train will take place in Pamplona this Saturday, called by the platform AHT Pause, at 12:00 hours from the Provincial Council. The construction of the railway line between Castejón and Pamplona continues and the Spanish Ministry of... [+]

Adif says that the situations of labor slavery denounced in the works of the AHT are "false"
After receiving the scandalous testimony that AHT Geldi denounces the existence of situations of labor slavery in the works of the High-Speed Train of Navarre, the company Adif that promotes these works has had to respond publicly: "They're a lie."

AHT Pause denounces the existence of situations of slavery in the works of the AVE of Navarre
The workers of the fast train that is being built in Navarre denounce that they are in a state of slavery during the press conference of the association AHT Pause in Pamplona.

They denounce that the AVE will lead to a large expropriation of agricultural lands in Álava
Representatives of the Añana and Trebiñu gangs, as well as farmers and ranchers in Álava, have denounced that they suffer "enormous institutional contempt" for the work of the AVE. More than two million square meters of “fertile land” will be expropriated in these places... [+]

For a quality public rail service for the Ribera

In recent weeks we have been reading "proposals" for the recovery of the railway line Castec-Soria and the maintenance of the Tudela train station in its current location, or for the construction of a new high-speed station outside the urban area with the excuse of the supposed... [+]


2024-12-18 | ARGIA
The Basque Y will not connect with Ipar Euskal Herria until at least 2042
The French Government has confirmed to the Spanish Government that the High-Speed Train will not reach Hego Euskal Herria (Irun link) until at least 2042 years later. It is not among the priorities of Paris.

Eguneraketa berriak daude