The Government of Spain provisionally provides the conventional rail lane for the TAV of Navarra

  • The Ministry of Transport proposes this as a temporary solution, which would be maintained until the Navarre TAV platform is operational between Castejón and Zaragoza.  

02 November 2023 - 10:49
Last updated: 12:00
Nafarroan abiadura handiko trena. // Argazkia: Wikimedia Commons CCA by 2.0 Generic

Between Arrizabalaga and Castejón a double platform for the high-speed train is being built. In this respect, the Ministry of Transport proposes — at least on a provisional basis — that this platform should have the width of a railway using the traditional railway. It would therefore be in line with the international standard width of the railway, 1,435 millimetres, throughout its journey. It aims to maintain the TAV platform between Castejón and Zaragoza in operation.

According to the Diario de Navarra, the Dean of Navarre of the Colegio de Ingenieros de Caminos, Canales y Marinas, Pedro Busto, pointed out that this temporary option has “much” but also contemplates “risks”: “Among other things, the negative differences are that this change is maintained over time and that it is maintained for 30 or 40 years with the current station of the San Jorge neighborhood.” Busto also stresses that the Etxabakoitz station project risks following “sine die”.

The Ministry has indicated that the platform under construction for the TAV is expected to be finalised by 2026 or 2027. It will therefore be connected temporarily with the Bilbao-Casetas (Zaragoza) line to avoid its disuse.

Speed change

For its part, the Department for Territorial Cohesion of the Government of Navarra stated that with the change the train will also reach a "high speed": “This does not depend on the width but on the new train platform that reduces the slopes and curves.”


You are interested in the channel: Abiadura Handiko Trena
Larunbatean manifestazioa egingo dute Altsasun: "Trena benetako garraiobide bihurtu dadin"

AHTren kontrako eta trenaren aldeko eragileek deituta, manifestazioa egingo dute Altsasun apirilaren 20an, larunbatarekin, tren-azpiegiturak berritu eta trenen maiztasuna handitzea eskatzeko. Alternatiba bat badagoela gogorarazi dute deitzaileek eta azterketa hori aurrera... [+]


Baskoien beste herrixka baten aztarnak aurkitu dituzte Nafarroan eta AHTren lanek suntsitu ditzaketela salatu dute

Muru Artederreta herrian, Murugain izeneko muinoan, Burdin Aroko herrixka baten horma agerian geratu da, AHTren lanentzako laginak hartzen ari zirela.  Bizilagunen hango elkarteak salatu du trenarentzako tunel baten ahoa eraikitzeak harresiaren zati bat suntsituko lukeela.


Julio Villanueva (AHT Gelditu)
"Abiadura Handiko Trenik gabeko Nafarroa posible da"

Abiadura Handiko Trenaren inguruan mintzatu dira zenbait ekintzaile asteazkenean Iruñeko Zabaldin osatu duten hitzaldian. Italiako Val Susa bailarako adibidea bertatik bertara ezagutzeko aukera ere izan dute han sortutako mugimenduaren ordezkari bat etorri delako... [+]


Iñaki Arriola notes that to see the works of the TAV completed it will still take a few years
The Councillor for Transport of the Basque Government has acknowledged that citizenship is "tired and annoying" with the duration of the works. It is promised that the works of the concrete infrastructure of the so-called "Basque Y" will end in 2025, but the entire upper structure... [+]

Request in Altsasu / Alsasua the adaptation of the current railway for the TAV and the social train